Uphill struggle to cool Fukushima 1 unit 1

After pumping increased amounts of water into the reactor core of Fukushima 1 unit 1 with the aim of bringing it to a “cold shutdown”, TEPCO had to conclude that the water level in both the reactor core and the containment is much lower than expected and their plan appears not to be succeeding.

Previously it was believed that the lower half of the fuel rods in the reactor pressure vessel (RPV) was covered in water. Now it appears that part of the RPV is dry and the fuel rods (or what’s left of them) are fully exposed. However, due to the damage to the rods much of the uranium pellets inside may already have spilled into the bottom portion of the RPV and may thus receive some cooling after all. TEPCO had only recently revised its estimate of core damage for unit 1 down from 70% to 55%.

The plan to provide ouside cooling to the RPV by flooding the dry well of the containment surrounding it with enough water to raise the water level to above the top of the fuel rods has not worked yet. Even after pumping more than 10,000 m3 of water, the water level in the 7,400 m3 containment is still below half, not even reaching the bottom of the RPV, let alone its top.

If the water level doesn’t rise further because of leaks then it seems quite unlikely that it will be possible to repair those leaks using manual labour, especially at dose levels of 10 millisievert and more per hour. Even when it looked like the plan might work for unit 1, it was questionable if the same procedure could then be applied to unit 2 or 3, which were already assumed to have a leaky containment.

TEPCO has not yet discussed any alternative plan if flooding the containment won’t work for some or all of the units.

See also:

TEPCO sends workers into unit 1 of Fukushima I

TEPCO has taken the first step towards installing new heat exchangers in wrecked reactors at its Fukushima 1 nuclear power plant that have suffered core damage after a cooling system failure. The objective is to achieve “cold shutdown”, which means that cooling water in the reactor remains below 100 degrees C and the pressure is at atmospheric level. Currently the water inside units 1, 2 and 3 is still boiling.

During normal operation, sea water cools steam coming out of the power turbine that generates electricity. It condenses it back to water, which goes back into the reactor core to be turned into setam again. After a shutdown, electric pumps and a separate heat exchanger, known as the residual heat removal system (RHR), take over the core cooling function. TEPCO had been aiming to restore the RHR since about March 20, when it reestablished a grid connection into the turbine hall, but found that the pumps are no longer usable.

The new system will not cool the core directly, which after the fuel rods partially melted is highly contaminated, but instead will circulate water to the containment vessel that surrounds the core, cooling the central part of the reactor from the outside rather than from inside. To that purpose, water will be pumped from a pipe connected to the containment to a heat exchanger, which passes the heat to an external water cycle that will be cooled using air. The original cooling system depended on sea water for condensing steam in the inner cycle, but the sea water intake system was flooded and destroyed by the tsunami, along with most of the diesel generators that provided power to all emergency pumps.

Before any work can be performed inside the reactor building, which no human had entered since the hydrogen explosions around March 12-15, the level of radiation there has to be brought down considerably. To that purpose a pair of hose pipes has been laid through the airlock and hooked up to a filter. Until at least May 16 air will be pumped through a filter set up outside the building. US-made robots sent into units 1 and 3 measured radiation levels of up to 49 mSv/h in unit 1 and up to 57 mSv/h in unit 3 on April 18. The dose inside the airlock of unit 1 was 270 mSv/h, in unit 3 it was 170 mSv/h. The typical background radiation dose for a civilian is 2-3 mSv per year. TEPCO hopes to be able to reduce radiation inside the building by a factor of 20.

Work will start with unit 1, because unlike unit 2 and 3 its containment vessel is assumed to be intact. Unit 2 and 3 are at atmospheric pressure. If they can’t maintain steam pressure they may also not hold water once they’re flooded. Also, because of a damaged torus (pressure suppression chamber), a lot more radioactivity has been leaking from unit 2 than from unit 1 and 3. That makes unit 1 by far the best candidate for trying out ideas on how to regain control and limiting further damage to the environment. However, there is no guarantee that, even if everything were to go perfectly on unit 1, any of the lessons learnt could be applied to the other units, since they may be too badly damaged to be repaired this way. The worst “patient” probably will be unit 2, which seemed to be leaking the most water. It isn’t clear how TEPCO is planning to deal with the leaking containments or the damaged torus. One approach might be to pump leaking water from the basement of the building back into the cooling system. TEPCO estimates 6 to 9 months for its “cold shutdown” plan.

Fallout prediction system went blind

Meanwhile it was reported that two systems meant to collect data from nuclear reactors and make predictions for nuclear fallout in Japan have failed to perform as intended. The Emergency Response Support System (ERSS) was supposed feed data from reactors into the System for Prediction of Envionmental Emergency Dose Information (SPEEDI). Both systems combined cost JPY 28 billion (about US$350 million), but ERSS failed along with everything else in Fukushima 1 when power was lost. It has yet to gather any data on the damaged units.

Radiation found on ocean floor

Caesium levels about 1000 times higher than normal have been found on the ocean floor 15-20 km from the Fukushima power plant, NHK reports:

The plant’s operator, Tokyo Electric Power Company, conducted its first contamination analysis of the seabed near the plant using samples from 2 points 20 to 30 meters deep on Friday.

Samples collected about 15 kilometers north of the plant contained 1,400 becquerels of cesium-137 per kilogram and 1,300 becquerels of cesium-134.

Samples taken around 20 kilometers south of the plant contained 1,200 becquerels each of cesium-137 and cesium-134 per kilogram.

The samples from the 2 points were also found to be contaminated with iodine-131.

TEPCO says it’s difficult to evaluate the readings as there are no official limits for these substances, but it will continue monitoring the radiation levels and their impact on seafood.

See also:

Fukushima watch 2011-05-01

The city of Koriyama in Fukushima prefecture, where top soil was removed from schools to reduce radiation exposure to children recently, is not only 50 km west of the Fukushima 1 nuclear power plant, it also lies in the heart of the central valley where most of the agricultural products of the otherwise mountainous region are grown.

Fukushima has already lost 90% of its fishing industry due to the tsunami. How much income will its farmers lose? Consumers can not be sure they will be safe if they eat crops produced in the region unless systematic testing takes place, but if high levels re found, farmers will demand compensation. How much will TEPCO have to pay and how much the government? In the 1950s nuclear power was sold to the public on the promise of being able to deliver electricity “too cheap to meter”. Now it could turn out as too expensive to measure.

Government advisor resigns in protest

Mr. Toshiso Kosako, a radiation export at the University of Tokyo has resigned as an advisor of the Japanese government, citing his opposition to raising permissible radiation exposure of school children. On April 19 the Ministry of Education and Scienced had announced a limit of 3.8 μSv/h (microsievert per hour), which is comparable to international maximum exposure rates of people working in nuclear power plants. Actually, 3.8 μSv/h times 24 hours times 365 days equals 33 mSv (millisievert), whereas in other countries the maximum permitted extra exposure on the job is 20 mSv, which comes on top of a natural radiation exposure of 2-3 mSv.

Radiation exposure of workers

Two workers at the Fukushima 1 nuclear power plant, employed by a sub-contractor of the power company, have been exposed to close to their maximum legal radiation dose:

The two workers have been exposed to 240.8 millisieverts and 226.6 millisieverts of radiation, respectively, when internal exposure is taken into account, among 21 workers exposed to over 100 millisieverts of external radiation since the crisis erupted following the magnitude 9 quake and tsunami, it said.

Under Japanese law, the Ministry of Health, Labor and Welfare has limited by an ordinance radiation exposure of each nuclear plant worker at 100 millisieverts a year in an emergency situation, but raised the limit to 250 millisieverts to cope with the Fukushima crisis on March 15.

The two were hospitalized for possible radiation burns to their feet after standing in water that contained radioactive materials 10,000 times the normal level while laying a cable underground at the troubled plant on March 24, the utility known as TEPCO said.

The limit for non-emergency work is 100 millisieverts over five years with no more than 50 per single year. These two workers received over 200 in a single month. The Ministry of Health and Welfare is planning to scrap the 50 mSv per year limit, leaving only the 100 mSv per five year limit in place for non-emergency workers. This is meant to make it possible to send workers from other reactors to Fukushima for cleanup work and still make it legal for them to absorb further radiation at regular work once they return.

Emergency power

TEPCO tested it’s mobile power generators at Higashidori nuclear power plant in Aomori prefecture on April 20 but revealed that the truck-mounted diesels had fuel for only 2 1/2 hours. If they have to provide power for longer they will need frequent refueling. In Fukushima 1 when the backup diesels failed it took about 9 days until grid power was restored inside the turbine halls to run electric pumps.

Radioactive contamination in unit 4 spent fuel pool

TEPCO has released updated numbers for radioactive contamination of the pool water in the spent fuel element pool of unit 4 of Fukushima 1. Here are the figures for 2011-04-29 (number for sample taken on 2011-04-13 in brackets):

  • Caesium 137 (half life: 30 years): 54,000 (was: 93,000 Bq/l)
  • Caesium 134 (half life: 2 years): 49,000 (was: 88,000 Bq/l)
  • Iodine 131 (half life: 8 days): 27,000 (was: 220,000 Bq/l)

Because 16 days have elapsed since the previous analysis, levels for iodine-131 should have halved twice (to about 55,000 Bq/l) while levels for both caesium isotopes should be virtually unchanged. Instead both caesium values dropped by more than 40% while Iodine is about 50% below the expected value. Where did the rest of the caesium and iodine go? There are several possible explanations.

Perhaps one of the analysises was simply wrong. That would not be out of the question, as TEPCO has had trouble with its figures before. More likely though, perhaps the water level was much lower on the first sample, meaning the current sample is diluted by a significant amount of added water (+72% water would explain the figures). That is to be hoped, because if the water level was in fact the same and the figures were correct then a lot of the pool water radioactivity would have had to escape into the atmosphere with steam or leaked with water to some other part of the reactor building.

Arnold Gundersen (YouTube, starting from 4:28) raised an interesting point about the isotope testing in the unit 4 pool: There’s too much iodine-131 for this to be from leaking fuel rods. The unit 4 reactor was shut down for maintenance on 2010-11-29, about 5 months ago. 151 days from 2010-11-29 to 2011-04-29 is close to 19 half lives for iodine-131, meaning only 2 millionths of the original iodine-131 levels should be left in the freshest nuclear waste in that pool, even less in older fuel rods. If 220,000 Bq/l came from atmospheric contamination (e.g. fallout from overheated unit 3 which is right next to it), then that is 220,000,000 Bq/m3 of water, left over after 4 half lives, so the original amount would have been 3,520,000,000. The pool is about 13m deep. To get it that radioactive, some 45,760,000,000 Bq/m2 had to land on the pool, which is a staggering amount.

Tepco revises core damage estimates

TEPCO has revised its estimates for the core damage in units 1, 2 and 3 of the Fukushima 1 nuclear power plant. It now estimates 55% (previously 70%) damage for unit 1, 35% (previously 30%) for unit 2 and 30% (previously 25%) for unit 3. The estimates are based on radioactivity levels measured inside the reactor containment.

TEPCO has experimented with pumping more water into the reactor core of unit 1 to fill the normally dry part of the containment vessel for cooling purposes:

TEPCO says it will raise the amount of water injected from 6 to 10 tons per hour for 6 hours, and then to 14 tons per hour. The temperature and pressure in the containment vessel will be monitored for 18 hours. The utility says it will decrease the flow back to 6 tons per hour by Thursday morning and then send robots into the reactor building to check for leaks. TEPCO also says it will make sure that the containment vessel, with the added weight of the water inside, can withstand strong aftershocks. The firm says robots on Tuesday detected radiation levels of up to 1,120 millisieverts per hour inside the No.1 reactor building. It says some contaminated water may be leaking from the reactor into external pipes. (NHK, 2011-04-27)

Radiation monitoring devices have been issued to 55 schools and kindergartens in Fukushima prefecture. Teachers will keep a log of radiation exposure of the children. At two schools in the city of Koriyama, some 50 km west of the wrecked reactor, workers are removing contaminated topsoil. The soil is first sprayed with water to prevent dust from rising through the work. The soil will be piled up and covered with sheets before later being moved to landfills.

One female worker in her 50s employed at Fukushima 1 received an accumulated dose of 17.55 mSv over the first quarter of the year, over three times the legal limit. She worked at the plant for 11 days after March 11. Most of the exposure was internal, through inhalation. By law female nuclear workers in Japan must not be exposed to more than 5 ms over any three month period.

See also:

Fukushima watch 2011-04-27

Tepco is preparing for a “wet tomb” for unit 1 and 3 of Fukushima 1. It stepped up its water injection for unit 1 from 6 m3/h to 14 m3/h today to test for leaks. It is using robots to visually inspect the inside of the reactors for signs of water leaking.

By allowing water from the reactor pressure vessel (RPV) to overflow into the containment that surrounds it, almost all of the RPV will be immersed in water, which will carry away heat from the fuel rods inside the RPV through conduction. 7,800 tons of water will be injected. If the water starts leaking from the containment, the plan will have to be abandoned. Concern has been raised how the extra weight would affect the seismic stability of the building in the event of another major quake.

Radioactive water has been found in the basement of the turbine building of unit 4, which was shut down at the time of the tsunami and does not have any fuel loaded in its core. The water is assumed to have leaked across from adjacent unit 3.

Tepco has released a radiation map for the Fukushima 1 plant, showing known radiation “hot spots” around the site.

Power companies operating nuclear power stations in Japan have deployed vehicle-mounted mobile backup generators at their plants, but in many cases their capacity is too small to replace the fixed backup generators such as the ones that failed in Fukushima 1. Surprizingly, they don’t seem to be in much of a hurry to address that safety problem: Japan Atomic Power Co. is quoted by Kyodo as trying to purchase three generator trucks by March 2012 while Hokkaido Electric Power Co. wants to buy a second generator vehicle for its Tomari power station “within two years”.

See also:

From Chernobyl to Fukushima

Twentyfive years ago an accident at the Chernobyl unit 4 nuclear power station destroyed the reactor and released massive amounts of radioactivity into the environment. Contamination of vast areas of land, mostly in Belarus and Ukraine but also reaching as far as central and Western Europe, persists to this day. Most of the cesium-137 released that day has yet to decay.

It can be argued that the lessons of Chernobyl had been fading much more quickly than the radiation. With fear of Global Warming growing, the nuclear industry was pushing for new reactors to be constructed and old reactors, many of which had been constructed in the 1970s, to have their operating spans extended by another decade or two. One such reactor was Fukushima 1 unit 1, the oldest of the Fukushima reactors, which started up on March 26, 1971. Its original operating span of 40 years would have expired at the end of March 2011, but it had its license extended by another ten years in February. Unlike its siblings units 2 and 3, unit 1 was an older type called BWR3 (the others were of a type called BWR4). One difference between them is that the BWR4 has a Reactor Core Isolation Cooling (RCIC) system. During a loss of all grid and backup power a steam turbine running off decay heat in the core could still pump water from the Suppression Chamber into the reactor core. The BWR3 makes do with an isolation condensor, which relies on electric pumps to cool and condense steam from the reactor using cold outside water. Once the pumps stop, the isolation condenser stops cooling steam. With the RCIC at least liquid water was being injected as long as there was battery power to control valves and the water in the suppression chamber wasn’t boiling yet.

According to the AREVA report, cooling in the isolation condenser in unit 1 stopped at 16:36 on March 11, less than an hour after the backup diesel generators had failed. By contrast, the RCIC pump in unit 3 continued until 02:44 on March 13, about 35 hours after loss of backup power. In unit 2 the RCIC survived until 13:25 on March 14, some 46 hours after the accident.

Immediately after the emergency stop (“scram”) of the reactors, the fuel rods were still producing 6% of the original thermal output in decay heat, which is why cooling was desperately needed. After 24 hours the decay heat had dropped to 1% of original output. From there it takes another 4 days for the output to drop by half again (0.5%). Without adequate cooling, the water level inside the reactor drops and the steam pressure in the reactor pressure vessel (RPV) goes up. At some point a valve opens and steam is released into the suppression chamber (wet well) at the bottom of the reactor. Once the water level drops too far the exposed fuel rods overheat until zirconium cladding gets damaged and nuclear waste starts leaking from inside the fuel rods. At 1200C the zirconium rods start burning in a steam atmosphere, releasing hydrogen as a byproduct. It was estimated that in unit 1 between 300 and 600kg of hydrogen were produced that way (300-1000 kg in units 2 and 3, which hold more fuel). The hydrogen leaks through the water in the wet well into the dry well. This is the first containment of the reactor, which is designed for a pressure of a little over 4 bar. If the containment pressure gets too high, there is no alternative but to release steam and hydrogen from the containment into the environment, along with radioactivity from the damaged fuel rods.

Unit 1 was completely without cooling water for 27 hours (until 20:20 on March 12). Units 2 and 3 were without cooling water for 7 hours (until 20:33 on March 14 and 09:38 on March 13, respectively). Because of the far longer period without cooling, 70% of the fuel assemblies in unit 1 is estimated to be damaged, versus 30% in unit 2 and 25% in unit 3. Perhaps if unit 1 had also had an RCIC system like units 2 and 3, it could have avoided that high degree of fuel damage. All three units were designed before the Three Mile Island (TMI) accident that highlighted the risks of losing core cooling and consequent hydrogen buildup.

When the containment vessel is vented, the gases are normally scrubbed (filtered) before being fed into a pipe that goes up a tall steel tower located between two of the units (1 and 2, 3 and 4, 5 and 6). That is not what happened. In units 1 and 3 radioactive steam and hydrogen ended up leaking into the upper part of the reactor building, the service floor above the containment, where the spent fuel pool and a crane for refueling and unloading the reactor are located. After TMI, hardened pipes were installed in US boiling water reactors for venting gas, but apparently Tepco didn’t think it was worth spending money that could instead be paid to its shareholders as dividends. Perhaps the leak occurred because insufficiently robust venting pipes had already been damaged by the initial earthquake, or perhaps the pressure was too high because Tepco waited too long with venting, hoping to still get pumps going again in time and save its capital investment. Whatever the reason, had the venting occurred through the tower, the reactor buildings might have survived and the spent fuel pools wouldn’t be lying full of debris from the collapsed structure now.

As an engineer, I know how difficult it is to build and operate complex systems. Often you might hear engineers confess they’re glad what they’re designing wasn’t used to run a nuclear power station, or fly an aircraft or run medical equipment. It’s one thing when failure of technology causes loss of data or loss of money, but it’s quite another if people die as a result. That is a grave responsibility.

Most of us engineers are aware of our imperfections. It takes careful design and implementation to build mission-critical systems. For example, a friend of mine was working on the avionics of the Airbus A-320, the first fly-by-wire commercial aircraft. Airbus had multiple programmers implement the software in different programming languages and using different hardware platforms in order to ensure that it was as unlikely as possible that if one system failed the other would be in trouble too. Environments such as airlines and nuclear power stations require a corporate culture where safety is always the top priority. Not cost, not convenience, not customer expectations — only safety.

That is not how Tepco has been operating. They have been caught red handed, again and again. One of the most embarrassing cases even involved Fukushima 1 unit 1:

Faked pressure test
Yet in the most serious case of all, Tepco officials are alleged to have faked a pressure test designed to test the integrity of the containment building. The test involves pumping nitrogen gas into the building to increase the pressure to about three times atmospheric pressure, then taking pressure readings to measure the leak rate.

Regulations state that the leak rate must be less than 0.45% per day. However, at Fukushima I-1 in 1992, the company conducted its own tests before the government inspectors turned up, and discovered that the building might not pass the test. One source quoted in the Daily Yomiuri said that leak rates fluctuated from 0.3% to 2.5% per day.

Documents found at Hitachi by Tepco’s own investigative team describe a method to fake the test by secretly pumping in extra air from the main steam isolation valve. At the time, Hitachi had a contract to check Tepco equipment. It is alleged that Tepco officials followed this procedure when the government inspectors were checking the leak rate.

Japan: nuclear scandal widens and deepens (WISE, 2002-10-04)

It has been argued that nuclear power could never be safe in a country so criss crossed with earthquake fault lines as Japan is. But the forces of nature are not the only challenge facing nuclear technology. Chernobyl exploded because of operator errors. Fukushima failed because of mistakes made by the humans who designed and operated it. The Fukushima I nuclear disaster was a man-made disaster, with a natural disaster acting only as the trigger.

In 2001 and again in 2009, researchers had published evidence of past huge tsunamis in the region, which were ignored by the nuclear industry. Fukushima 1 was kept running, without any upgrade to its breakwaters. When the quake struck on March 11, 2011, unit 1 was set to operate until 2021, without the reactor core isolation cooling system that the other units have had since the 1970s and without the upgraded venting systems that US reactors have had since the 1980s.

Instead of thinking of ways to upgrade these ancients plants to at least make them a little bit safer, Tepco was being creative only in dodging vital inspections, for example to hide their leaking containment that was supposed to protect the tens of thousands of people living near the reactors. Extending the lifetime of the plants by another 10 or 20 years with the least amount of money spent was going to be profitable to Tepco shareholders. As a result, hundreds of square kilometers have now become a nuclear wasteland, 90,000 people have lost their homes and probably over a trillion yen (US$12 billion) will have to be spent on cleaning up the mess at the reactor site over a number of years.

See also:

Japan’s nuclear future (or what’s left of it)

Tokyo Electric Power Company (Tepco) president Masataka Shimizu was turned down twice when he requested a meeting with Fukushima prefecture governor Yuhei Sato who was very upset about the insufficient safety of Tepco’s nuclear power plants in the prefecture, which were not designed to cope with a tsunami the size triggered by the March 11 quake. Tepco was unable to reestablish cooling for too long, leading to core damage, forced venting of radioactive gas, hydrogen explosions that destroyed reactor buildings and spread radiactivity, a cracked containment, leaks of radioactive water, damage to reactor cores and to spent fuel pools.

Large parts of Fukushima prefectures are radioactively contaminated now. Agricultural and fishery products from the largely rural prefecture will have difficulties finding buyers, even if they were to meet Japanese safety regulations.

Some 80,000 people in a 20 km radius around Fukushima 1 (an area of about 600 square kilometers or 60,000 ha) have lost their homes and will now be prohibited on penalty of a fine of up to 100,000 yen (about US$1,200) or 30 days in jail from returning. The evacuation zone will now be extended to Iitate, Katsurao, Namie and parts of Minamisoma and Kawamata, which lie between 20 and 50 km northwest of Fukushima 1. Another 10,000 residents will be affected by that extension. In Namie, at the edge of the 20 km exclusion zone, backround radiation of 49.8 μSv/h was measured. The natural rate in Japan before the accident was between 0.02 and 0.06 μSv/h. Other notable readings were 3.5 μSv/h in Toyota town some 50 km to the west, 15.5 μSv/h in Iitate, some 30 km to the Northwest and 28.6 μSv/h in Namie 30 km to the Northwest. The current post-accident rate in Tokyo, 230 km to the south, is about 0.08 μSv/h, twice its pre-accident rate. Residents of the newly condemned areas have one month to move out.

Inside the exclusion zone even higher values have been measured, for example around 50 μSv/h in several locations 4-5 km from the plant and 110 μSv/h just over 3 km West of the plant. Under these circumstances, it seems almost unbelievable that Tepco was still talking about restarting units 5 and 6 of Fukushima 1, which lie only a few hundred meters from the wrecked units and had also been surrounded by seawater during the tsunami, but were shut down for maintenance at the time. Who is going to work in those plants and under what working conditions? As of April 21, the radiation level at the South side of the administration building located half way between units 1 and 5 was an astounding 490 μSv/h.

Prime minister Kan has made it clear that he does not want to see units 5 and 6 restarted, but made no mention of Fukushima 2, which is located about 11 km South of Fukushima 1 and 9 km inside its exclusion zone (and inside its own 8 km exclusion zone, which is completely enclosed by the larger 20 km exclusion zone imposed around Fukushima 1). Tepco is pushing for being allowed to restart Fukushima 2 as soon as possible, but Fukushima governor Yuhei Sato opposes the idea.

Before the disaster Japanese power companies had been planning to build enough new nuclear power stations to push the nuclear share of electricity generation from 30% to 50%. It remains to be seen, where they would like them built and what the local population and politicians will have to say about that. I am sure the residents of existing reactor sites are watching very closely as 90,000 of their fellow citizens are being evicted from their homes, their livelihoods destroyed, their communities devastated and ripped apart, their regional agricultural products shunned on supermarket shelves.

How much money do you have to pay a quiet town or village somewhere on the Japanese coast to agree to accept another nuclear power station? I still believe there are some things you can not buy with money. I grew up in Eastern Bavaria, some 30 km from the village of Wackerdorf, which the Bavarian state government had selected as the site of a huge nuclear waste reprocessing plant in the 1980s. Local unemployment was high, so the government thought the promise of jobs and local tax revenue would win over the locals, but nevertheless resistance turned out to be fierce. For years the struggle tore the country apart. Families from grandmother to grandchild would walk to the construction site fence every weekend to protest. Then came April 26, 1986: After the Chernobyl disaster the plan became a lost cause. It was officially withdrawn 2 years later.

I don’t expect Japan will rush to shut down its existing nuclear power plants. However, it will become next to impossible to build new reactors (14 are planned by 2030). Especially the oldest reactors and the most seismically vulnerable ones will receive increasing scrutiny because of a nervous local (and national) population. This is not the end of nuclear power in Japan, but it may be the beginning of the end.

Fukushima watch 2011-04-22

Tepco is talking about plans to cool units 1 and 3 of Fukushima 1 via the containment vessel. The water level inside the usually dry portions of the containment (called the dry well, D/W) will be raised high enough to flood the exterior of the reactor pressure vessel (RPV) up to the top of the fuel rods. Normally only the inside of the suppression chamber (S/C, a circular pipe running around the bottom of the RPV) is filled with water. Tepco thinks the reinforced concrete of the dry well is sturdy enough to take the weight of the water and is now seeking the approval of the nuclear regulators.

The US NRC has previously voiced concerns about the safety of the containment in earthquakes when filled with large amounts of water:

When flooding containment, consider the implications of water weight on seismic capabilities of containment.

Unit 2 is not included in the plan because its suppression chamber appears to have suffered damage in an explosion on March 15 and has probably been leaking since then. Most of the highly radioactive water in a trench under the turbine hall is assumed to have leaked there from unit 2. It is not clear if or how those leaks can be plugged.

Tepco has requested French nuclear company AREVA (which is also its supplier for nuclear fuel) to set up a plant for decontaminating radioactive water at the reactor site. This would make it less risky to move the water to the nuclear waste plant in Rokkasho village, Aomori prefecture or for recycling it as cooling water.

Yesterday I experienced my first earthquake since returning to Tokyo. It was a M6.1 quake centered under Chiba, some 60 km from Tokyo. During the night I was woken up by a M5.6 quake that hit Fukushima.

UPDATE 1: Tepco will be short of 8500 MW this summer

Tepco’s maximum supply capacity today is 38.4 GW (one Gigawatt is 1,000 Megawatt or 1,000,000 Kilowatt). The forecast maximum demand today is 34 GW. Hence there will be no rolling blackouts today. For comparison, last year’s peak demand around this time was about 44 GW.

Tepco expects power demand to stay moderate in the near future, due to mild temperatures and the Golden Week holidays in May, rising to about 38 GW by the end of May. By then it hopes to have restored enough supply capacity for a celing of 39 to 42 GW. Tepco expects to have 46.5 GW online this summer versus a demand peak of 55 GW. Last year’s exceptionally hot summer even saw a peak load of 59.9 GW.

Tepco’s customers will largely have to give up on air-conditioning this summer or periodically lose all electric power. Perhaps after Cool Biz it is time to go one better and recommend Bermuda shorts.

UPDATE 2: Rising pressure in unit

Pressure in the reactor pressure vessel (RPV) of Fukushima 1 unit 1 has gradually increasing since March 24, when it was below 0.5 MPa (about 5 bar). On April 19 according to a NISA report it was at 1.141 MPa (about 11 bar) according to sensor B, while sensor A indicates 0.524 MPa. It is not clear how much the nitrogen being injected is responsible for the rise in pressure and how much may be due to a buildup of hydrogen, but the pressure buildup started two weeks before the nitrogen injection, which was started in response to the rising pressure.

NISA status reports:

Update 3: Spent fuel pools comparison – unit 2 and unit 4

A week ago I wrote here about the results of radioisotope testing on water in the spent fuel pool of unit 4 of Fukushima 1.

There results for the unit 4 spent fuel pool were:

  • Caesium 137: 93,000 Bq/l (half life: 30 years)
  • Caesium 134: 88,000 Bq/l (half life: 2 years)
  • Iodine 131: 220,000 Bq/l (half life: 8 days)

For comparison, here are the figures from an analysis of water in the skimmer surge tank of unit 2, taken on April 16. The skimmer surge tank is an overflow container adjacent to the spent fuel pool into which water can splash or overflow from the main pool. Tepco tested it to get ideas for installing a heat exchanger and decontamination unit for the pool.

Here are the unit 2 skimmer surge tank figures:

  • Caesium 137: 150,000,000 Bq/l (half life: 30 years)
  • Caesium 134: 160,000,000 Bq/l (half life: 2 years)
  • Caesium 136: 4,000,000 Bq/l (half life: 13 days)
  • Iodine 131: 4,100,000 Bq/l (half life: 8 days)

The small container of sampled water radiated at 3.5 mSv/h at the surface, which is roughly 100,000 times the natural background radiation level.

The caesium radioactivity of the skimmer surge tank water in unit 2 is about 1000 times higher than water in the spent fuel pool of unit 4. However the shortlived iodine is only about 20 times more active. This could suggest the radioactivity is from damaged fuel rods in the spent fuel pool and not the adjacent damaged unit 2 reactor core. Spent fuel was unloaded into the unit 4 spent fuel pool more recently than into the unit 2 spent fuel pool, hence it will have a higher Iodine-131 to caesium ratio. The higher caesium activity in unit 2 suggests more damage to fuel rods, but in the case of iodine this is partly counterbalanced by a longer nuclear decay since the last unload from the core into the pool compared to unit 4.

Return to Japan

After a bit over a month in Germany we’re back in Tokyo again. This doesn’t mean I think it’s safe here: Bad things could still happen at Fukushima 1 or elsewhere in Japan. Radioactivity may still be leaking for months from the wrecked nuclear power plant. However we have two kids enrolled at schools in Tokyo whose continued education was at risk if we stayed away longer. Meanwhile unlike up in Fukushima, background radiation levels in Tokyo are supposed to be no higher than in Bavaria, if you trust published figures. As long as no more hydrogen explosions happen, some form cooling is maintained for the reactor cores for the next couple of years and the spent fuel pools get topped up regularly it seems likely that the worst is behind us. The situation at Fukushima 1 will remain severe for a long time, but everywhere else it may stabilize.

There is still a lot of concern about contamination of food from areas closer to the nuclear ruins, or anywhere where rain fell soon after Tepco was forced to vent the uncooled reactors when it couldn’t get cooling pumps restarted. Background radiation spiked on the first weekend, then dropped again around the Kanto area, then picked up again when rains fell during winds from Fukushima around March 21-24. Radiation in rain and dust (in Bq/m2) peaked during those days in the Kanto area:

Sampling period Iodine-131 (Bq / m2) Cesium 137 (Bq / m2) Remarks
2011/04/20 9:00 – 2011/04/21 9:00 20.4 20.8 Rain
2011/04/19 9:00 – 2011/04/20 9:00 Not detectable (ND) 29.8 Rain
2011/04/18 9:00 – 2011/04/19 9:00 55.7 Not detectable (ND) Rain
2011/04/17 9:00 – 2011/04/18 9:00 Not detectable (ND) 14.8  
2011/04/16 9:00 – 2011/04/17 9:00 Not detectable (ND) 6.31  
2011/04/15 9:00 – 2011/04/16 9:00 Not detectable (ND) 4.75  
2011/04/14 9:00 – 2011/04/15 9:00 Not detectable (ND) Not detectable (ND)  
2011/04/13 9:00 – 2011/04/14 9:00 Not detectable (ND) Not detectable (ND)  
2011/04/12 9:00 – 2011/04/13 9:00 Not detectable (ND) 4.02  
2011/04/11 9:00 – 2011/04/12 9:00 100 169 Rain  
2011/04/10 9:00 – 2011/04/11 9:00 2.99 5.18  
2011/04/09 9:00 – 2011/04/10 9:00 19.4 7.9 Rain
2011/04/08 9:00 – 2011/04/09 9:00 8.9 11.7  
2011/04/07 9:00 – 2011/04/08 9:00 5.25 Not detectable (ND)  
2011/04/06 9:00 – 2011/04/07 9:00 6.22 10.3  
2011/04/05 9:00 – 2011/04/06 9:00 8.17 5.57  
2011/04/04 9:00 – 2011/04/05 9:00 16.9 5.94  
2011/04/03 9:00 – 2011/04/04 9:00 20 17.5  
2011/04/02 9:00 – 2011/04/03 9:00 Not detectable (ND) 8.03  
2011/04/01 9:00 – 2011/04/02 9:00 Not detectable (ND) 14.5  
2011/03/31 9:00 – 2011/04/01 9:00 37.6 26.1  
2011/03/30 9:00 – 2011/03/31 9:00 50.1 68.4  
2011/03/29 9:00 – 2011/03/30 9:00 21.3 5.35  
2011/03/28 9:00 – 2011/03/29 9:00 36.9 18.1  
2011/03/27 9:00 – 2011/03/28 9:00 45.5 5.52  
2011/03/26 9:00 – 2011/03/27 9:00 101 35.9  
2011/03/25 9:00 – 2011/03/26 9:00 217 12.2  
2011/03/24 9:00 – 2011/03/25 9:00 173 36.9  
2011/03/23 9:00 – 2011/03/24 9:00 12 790 155 Rain
2011/03/22 9:00 – 2011/03/23 9:00 35 700 335 Rain
2011/03/21 9:00 – 2011/03/22 9:00 32 300 5300 Rain
2011/03/20 9:00 – 2011/03/21 9:00 2880 561 Rain
2011/03/19 9:00 – 2011/03/20 9:00 39.8 Not detectable (ND)  
2011/03/18 9:00 – 2011/03/19 9:00 51.4 Not detectable (ND)  

Until consumers are reassured via broad and thorough testing of food, I think a lot of buyers will avoid food from the whole region (Fukushima and adjacent prefectures), even if radiation in food near or exceeding legal limits was measured mostly inside the evacuation zone (where everybody is forced to leave now) and an area Northwest of it that may also get evacuacted. The government has dragged its feet too much to be able to maintain confidence, for example in Iitate, where both Greenpeace and the IAEA (as unlikely a couple as any) drew attention to radioactive contamination levels warranting evacuation before the government finally asked inhabitants to leave within one month.

Bottled water seems in demand in Tokyo even though, according to the Tokyo water board, caesium-131 and other radioisotopes are below detection levels now.

Nuclear, wind and sockets

Businesses and households are trying as hard as they can to save electricity, after Tepco lost 15 GW of generating capacity, forcing it to impose rolling blackouts. It hopes to restore 5 GW of capacity before the summer by installing gas turbines at existing thermal power plant sites. The situation reminds me of a tongue in cheek advertising slogan used by the nuclear industry in Germany in the 1970s: “Why nuclear power? My electricity comes from the socket!” The nuclear lobby was trying to paint its opponents as ignorant people who had no idea how to secure supplies. It is this arrogant we-know-it-all attitude that has led to disaster and consequently to a disruptive power shortage. “Why alternative energy? My electricity is supplied by Tepco!” is how people were led to think. Millions of sockets in Eastern Japan have been without power because of this, not to speak of tens of thousands evacuated from a nuclear waste land.

Japan has ample potential for geothermal and wind power. It has thousands of km of coastline that could be used for offshore wind farms, yet in 2010 a mere 2.3 GW of wind power was installed, compared to 27.2 GW in Germany. Four of the German states (Sachsen-Anhalt, Mecklenburg-Vorpommern, Schleswig-Holstein, Brandenburg) already get between 47 and 38 percent of their annual electricity production from wind power, far bigger than Tepco’s pre-Fukushima share of nuclear power.

Those junior nuclear engineers

If you thought things were getting back to normal here, think again: In a surprise move, the Japanese Ministry of Education has set a limit of 3.8 microsievert/hour for children in kindergartens, elementary schools and junior high schools. Multiplied by 8 hours a day, 6 days a week for one year it is 10 millisievert per year. This is in fact half the annual limit of radiation exposure that applies to workers in the nuclear industry in Germany, even though children are more sensitive to radiation damage than adults. No, this is not a late April Fool’s joke. Just like nuclear workers, teachers in Fukushima will be issued portable dosimeters to be able to verify that kids stay under the limit. 3.8 microsieverts per hour is about 40 times the current background radiation level in Tokyo. I must admit, that is one of the weirdest developments I have come across in the whole Fukushima disaster so far.

See also:

Tepco has a plan for Fukushima

The New York Times reports that Tepco has announced a timeline for securing the wrecked Fukushima 1 nuclear power plant:

The first part of the plan would take about three months and include installing a cooling system to lower the temperature in the reactors and spent fuel pools, as well as reducing radiation in the surrounding area, said Tsunehisa Katsumata, the chairman of Tokyo Electric.

The second part, which would take an additional six months, would include more pumping of water, the introduction of a new heat removal system and reducing the amount of contaminated water. The wreckage from three of the four most severely damaged reactor buildings would then be removed and the reactors inside would be covered.

While this vague outline is the most concrete recovery plan to date, it is of course subject to what is physically possible. Intentions, even with an approximate time scale, do not in any way prove that the plan is workable.

Let us remember that on the weekend following the quake and tsunami, Tepco moved mobile diesel generators onto the reactor site hoping to restart the cooling pumps using mobile emergency power, but found that the power connections were incompatible and the electrical switches had been destroyed by sea water. That plan had to be abandoned.

Then Tepco installed a fresh external power line and a new switch panel to restart pumps with restored grid power, but no further progress has been made in getting the original cooling pumps going again. That plan has been quietly abandoned and Tepco is still using temporary electrical pumps that inject fresh water from a nearby dam. There is no closed circulation system in place. Unlike the purified fresh water normally used for cooling, the dam water can contain small amounts of calcium that can clog pipes and valves.

Tepco no longer seems to publish how much water is being injected per hour into the three units. It also seems to have stopped publishing radiation figures for the drywell and suppression chamber, perhaps to avoid questions about a sudden major spike of radiation in unit 1 after the April 7 quake.

No explanation is being given about what is happening to all the injected water, how much re-condenses from steam into the reactor drywell (primary containment) or suppression chamber or leaks in liquid form into these areas and how much may be leaking outside the reactor containment or is released as steam (the containments of unit 2 and 3 are at atmospheric pressure). The NRC suspects that the circulation pump seals at units 1 through 3 are damaged, allowing water to leak. Probably Tepco doesn’t tell us where the water goes because nobody (including Tepco) really has any data.

It’s easy to say it will take three months to install a new cooling system, but if even one of the units still leaks large amounts of water too radioactive to go near it, that’s going to be a tough plan to implement. It’s not enough to get water into the reactor and to cool water or steam coming out of the reactor with a heat exchanger, all of this also has to happen without massive leaks that continually carry out radioactivity from damaged fuel rods. Many more afterquakes expected in the region for the rest of the year, some of them at magnitude 7 and greater, will complicate the recovery.

The recovery plan for Fukushima 1 will remain an uphill struggle for many months to come.

See also: