Chernobyl in the basement

TEPCO has released radiation figures for the 2700 t of water in the basement of unit 1 of the Fukushima 1 nuclear power plant:

Tokyo Electric Power Co. <9501> said Monday that the amounts of radioactive materials in water at a reactor building of the Fukushima No. 1 nuclear power plant were about 10,000 times the normal levels for water inside a nuclear reactor.
The water, recently found in the basement of the No. 1 reactor building of the nuclear power plant, contained 30,000 becquerels of iodine-131 per cubic centimeter, 2.5 million becquerels of cesium-134 and 2.9 million becquerels of cesium-137.

(Jiji Press, 2011-05-30)

A total of 2700 t of water are estimated to be in the basement. That works out as 6.75E15 Bq = 6.75 PBq of Cs-134 and 7.83 PBq of Cs-137. For comparison, the total radioactive release from Chernobyl is estimated at 48 PBq of Cs-134 and 89 PBq of Cs-137. That means the water in the basement of unit 1 alone contains about one tenth of all the radioactivity released into the environment by the Chernobyl disaster. When the accident started, we were told that “Fukushima is no Chernobyl” because unlike the Soviet reactor its reactors had containments. Unfortunately, they didn’t work. All that radioactivity mentioned above is already outside of the containment, in a place that was never designed to be flooded with thousands of tons of radioactive water.

Units 2 and 3 are assumed to be in equally bad shape as unit 1, as both suffered a meltdown and neither of those units’ containments still hold any pressure. All three units have flooded basements. Water in a trench near unit 2 was measured at 2 million becquerels of cesium-137 per cubic centimeters on March 30, quite similar in contamination to the unit 1 basement.

When people first entered unit 1 again on May 13, the water level in the basement of unit was reported to be 4.2 m. Two weeks later it is 4.6 m and the storage tanks at the reactor site are almost full. Very soon something needs to happen about that water. To complicate things even more, June is the rainy season in Japan, when typhoons can dump huge amounts of water onto Japan.

The water treatment plant built by Areva is expected to start operating around the middle of this month. TEPCO quoted the cost of decontaminating water with this system at 210,000 yen per ton (about US$2600). It intends to decontaminate 250,000 tons of water by the middle of January 2012, for a total cost of 53.1 billion yen (about US$650 million).

Currently 5 cubic meters per hour (m3/h) are being pumped into unit 1 for cooling, 4.9 m3/h into unit 2 and 12.5 m3/h into unit 3 (which is still overheating). That’s about 550 tons of water per day, which is assumed to leak into the basements of the three reactors, loaded with dissolved radioactive waste from damaged fuel rods. If cooling water feeds continue at current rates, there will be another 8,000 tons of highly radioactive water to be taken care of by the time AREVA’s treatment plant starts up — that is, if all goes according to plan…

A “mega-float” that has been towed to the site for storing and transporting radioactive water can probably only be used for decontaminated water (i.e. with 99.9% of the radioactivity removed), otherwise radiation would be too high to handle. Contaminated water being pumped from the basement of the turbine buildings to storage tanks gives off so much radiation that the piping is covered up with lead wool wherever people have to walk over it and is cordoned off with security tape everywhere else.

If a water pump fails and it has to be replaced, someone will have to disconnect and reconnect pipes to pumps that carry billions of becquerels of radioactivity per liter of water. There will be leaks and puddles and spills. This is not how things would be done if there was any choice.

Fukushima 1 may not make the headlines of the world media much any more, but the situation there is still nightmarish. It’s not the TEPCO managers who are paying for their company’s gross negligence, but unnamed workers of hired subcontractors who are risking their lives and health.

The cleanup and compensation for thousands who lost their homes and incomes through the fallout far exceeds TEPCO’s ability to pay, so tax payers will be forced to pay the bill, yet the government chose not to force TEPCO into bankruptcy. Its share price may have fallen, but its stock did not become worthless as say General Motors in the US car industry bail-out, or perhaps the crops grown by farmers nearby or the now deserted homes owned by families around the plant. TEPCO’s well-connected shareholders were effectively bailed out by the government at our expense.

See also:

Fukushima 1 unit 5 water pump fails

A failure of a sea water pump at unit 5 of the Fukushima 1 Nuclear Power Plant demonstrated the still volatile situation at the reactors. It allowed water temperatures inside the reactor (which had officially been in “cold shutdown” since March 20) to climb as high as 93 degrees C again before a replacement pump restored the water flow and allowed temperatures to drop again. Unlike the heavily damaged units 1 through 3, units 5 and 6 (along with unit 4) had been shut down for maintenance when the quake and tsunami hit. Due to their slightly higher elevation they escaped the worst of the tsunami. A single backup diesel generator for units 5 and 6 survived. So far TEPCO has not announced any plans yet to permanently decommissioning the two units, although the government of Prime Minister Kan pushed for that.

The failed temporary pump provides cool sea water to the heat exchanger of the Residual Heat Removal System (RHRS). TEPCO reports:

At 9:14 pm on May 28th, we found that one temporary residual heat removal system seawater pump of Unit 5 stopped. At 8:12 am on May 29th, replacement work to the spare pump started. After finishing the replacement work, we started the pump at 12:31 pm, and restarted cooling from 12:49 pm.

The RHRS is a cooling system that is used whenever the reactor does not drive a steam turbine, where heat is removed via the attached condenser unit. It is also used to cool the water in the spent fuel pools. Both a loaded reactor core and fuel elements in the pool produce decay heat that needs to be removed for months and years after a shutdown. Both the condenser and the RHRS require a steady flow of seawater to carry away heat.

According to a diagram at the NISA website Units 5 and 6 had been using a temporary pump near their regular cooling water intake channels, which suggests that the normal pumps of the RHRS had been damaged in the tsunami. TEPCO has now set up a new pump (as well as a spare next to it) halfway between the cooling water intake channel and the RHRS and cooling water circulation pumps. For the last two months there had been no spare in place.

Unit 1 dry well radiation levels

There have been some online discussions about spiking radiation level figures in the dry well (primary containment) of unit 1. Here is a graph from atmc.jp:

The original data for this graph are figures published by TEPCO/NISA of the CAMS radiation monitor readings for the three units. Until May 25 this data was available in daily updates on the NISA website under “Seismic Damage Information(the nnnth Release)(As of hh:mm May dd, 2011″, document “Fukushima Dai-ichi Nuclear Power Station Major Parameters of the Plant (As of h:mm, May dd)”. Since then NISA no longer seems to publish those figures. It can still be found vi the “Status of Fukushima Daiichi and Fukushima Daini Nuclear Power Stations after Great East Japan Earthquake” page on the TEPCO website though: Look for “The parameters related to the plants in Fukushima Daiichi Nuclear Power Station”, which has a link to the latest document and a ling to an archive page with previous daily data sets. “CAMS radiation monitor” has entries for D/W A and B, S/C aA and B. The D/W B sensor is the one in the above chart. Strangely, the numbers on the atmc.jp do not always match the data on the NISA/TEPCO sites:

5/18: NISA: 25.4 Sv/h / atmc.jp: 45.4
5/19: NISA: 36.3 Sv/h / atmc.jp: 36.3
5/20: NISA: 46.5 Sv/h / atmc.jp: 46.5
5/21: NISA: 36.2 Sv/h / atmc.jp: 36.2
5/22: NISA: 196 Sv/h / atmc.jp: 196
5/23: NISA: 33.1 Sv/h / atmc.jp: 201
5/24: NISA: 30.5 Sv/h / atmc.jp: 192
5/25: NISA: 204 Sv/h / atmc.jp: 215
5/26: TEPCO: 39.3 Sv/h / atmc.jp: 43.7
5/27: TEPCO: 53.5 Sv/h / atmc.jp: 63.8
5/28: TEPCO: 215 Sv/h / atmc.jp: 215
5/29: TEPCO: 225 Sv/h / atmc.jp: 225
5/30: TEPCO: 41.8 Sv/h / atmc.jp: n/a

The source of the discrepancy between the two sources is unclear as ultimately TEPCO must be the only source of data on the reactor.

Some people have speculated that the sudden increase in the graph indicates that a large amount of fuel melted through the pressure vessel and leaked onto the floor of the dry well. However, that would not explain why the values significantly dropped again and then shot back up again.

TEPCO states that they think the radiation sensors are malfunctioning. I suspect their explanation is the correct one, but how reassuring is that?

Trying to manage a badly damaged nuclear reactor (actually, 3 of them!) and the 4 loaded spent fuel pools next to them with broken instruments whose readings can not be trusted any more is a bit like trying to drive a car without a speedometer and with a shattered windscreen that prevents you from seeing the road, going only by the directions of your passenger who sticks his head out of the window to keep you on the road.

VIA PC3500 board revives old eMachines PC

Last September one of my desktop machines died and I bought a new Windows 7 machine to replace it. Today I brought it back to life again by transplanting a motherboard from an old case that I had been using as my previous Linux server. The replacement board is a VIA MM3500 (also known as VIA PC3500), with a 1.5 GHz VIA C7 CPU, 2 GB of DDR2 RAM and on-board video. It still has two IDE connectors as well as two SATA connectors, allowing me to use both my old DVD and parallel ATA HD drives, as well as newer high capacity SATA drives.

After the motherboard swap I had to reactivate Windows XP because it detected a major change in hardware. Most of the hardware of the new board worked immediately, I could boot and had Internet access without any reconfiguration. When I started with the new machine. I just had to increase video resolution from the default 640×480 to get some dialogs working.

I then downloaded drivers for the mother board and video from the VIA website. I now have the proper CN896 (Chrome IGP9) video driver working too.

When I tested the board as a server with dual 1 TB drives (RAID1), it was drawing 41W at idle. Running in my eMachines T6212 case with a single PATA hard drive it draws 38W at idle.

Before removing the old motherboard I made a note of all the cable connections on both motherboards. The front-mounted USB ports and card reader have corresponding internal cables, which connected to spare on-board USB connectors. The analog sound connectors connect to the motherboard too. The only port at the front left unconnected was the IEEE-1394 (FireWire / iLink) port, which has no counterpart on the VIA board.

It feels great to have my old, fully configured machine with all its data and applications back thanks to a cheap motherboard that works flawlessly.

Fukushima had new vents, but system failed

The New York Times reports that the reactors at the Fukushima 1 nuclear power plant were equipped with an improved system for venting steam in an emergency, but it failed to work. Originally it had been reported that TEPCO did not retrofit the units that had been online since 1970s with the new designs introduced in the US in the 1980s. However, it appears to have done so between 1998 and 2001.

The problem was, the improved system relied on the same sources of electricity to operate valves as the cooling system, so when the cooling system stopped working as diesel generators failed and dangerous levels of steam pressures built up, the venting system designed to protect the containment wasn’t working properly either. Instead of one system protecting the public if the other system failed, both had a single point of failure, their dependence on diesel generators in the flooded turbine hall basements.

The executives did not give the order to begin venting until Saturday — more than 17 hours after the tsunami struck and six hours after the government order to vent.

As workers scrambled to comply with their new directive, they faced a cascading series of complications.

The venting system is designed to be operated from the control room, but operators’ attempts to turn it on failed, most likely because the power to open a critical valve was out. The valves are designed so they can also be opened manually, but by that time, workers found radiation levels near the venting system at Reactor No. 1 were already too high to approach, according to Tokyo Electric’s records from the accident’s early days.

At Reactor No. 2, workers tried to manually open the safety valves, but pressure did not fall inside the reactor, making it unclear whether venting was successful, the records show. At Reactor No. 3, workers tried seven times to manually open the valve, but it kept closing, the records say.

The results of the failed venting were disastrous.

Reactor No. 1 exploded first, on Saturday, the day after the earthquake. Reactor No. 3 came next, on Monday. And No. 2 exploded early Tuesday morning.

The venting system could also have been damaged by the earthquake.

According to the NYT, the new venting system bypasses filters that hold back much of the radioactivity.

When TEPCO was talking about venting the reactors, before the spectacular hydrogen explosions, they reassured the public that the release of gas would be “filtered”. Either they were misleading the public, or they were talking about the old venting system, which was suspected of not being able to cope with the pressure of an emergency release, which is the very reason the new system had been introduced.

See also:

Fukushima cooling system switched off 10 minutes after quake

Data released by TEPCO on May 16 shows that apparently the isolation condenser, a cooling system that is supposed to protect the reactor after a shutdown, was manually shut down in unit 1 within 10 minutes of the earthquake.

When the quake hit at 14:46 on 2011-03-11, the power station lost its grid connection. Diesel generators sprang into life to provide backup power for the Residual Heat Removal System (RHR). Around 15:00 someone manually shut down the isolation condensor. About half an hour later tsunami hit the station. Within minutes the diesel generators failed and the RHR stopped. At that point the battery-operated pumps for the isolation condenser were the only system still able to remove heat from the reactor core, but the valve for this system had been closed by operators. From that point onwards the reactor core was entirely without cooling. Records show that at 18:10 the valve was open again. At 18:25 it was closed again and 21:30 it was open again. The isolation condenser finally failed at 01:48 on 2011-03-12, perhaps because its batteries ran out.

According to the AREVA presentation from 2011-04-07, the isolation condenser in unit 1 stopped at 16:36 on 2011-03-11, but perhaps that was based on incomplete or bad data from TEPCO.

See also:

Fukushima reactor damaged before tsunami

According to a Kyodo news report, extremely high radiation levels were measured in unit 1 of Fukushima 1 nuclear power station the night after the quake, hours before radioactive steam was first vented from the containment vessel at 04:00 the next morning (2011-03-12).

Workers entered the No. 1 reactor building during the night to assess the damage only to hear their dosimeter alarms go off a few seconds later, sources at Tokyo Electric Power Co. said. Since they thought the building was filled with highly radioactive steam, the workers decided to evacuate.

Based on the dosimeter readings, the radiation level was about 300 millisieverts per hour, the source said, suggesting that a large amount of radioactive material had already been released from the core.

The source of the steam was believed to be the No. 1 reactor’s overheated pressure vessel.

But for that scenario to hold, the pressure in the reactor would have to have reached enormous levels — damaging the piping and other connected facilities. It should have taken much more time to fill the entire building with steam.

A source at Tepco admitted it was possible that key facilities were compromised before the tsunami.

(Japan Times, 2011-05-16)

According to the AREVA presentation by Dr Matthias Braun, the reactor isolation condensor in unit 1 stopped working at 16:36 on 2011-03-11, 55 minutes after the diesel generators had been knocked out by the tsunami. After that, pressure from boiling water built up in the reactor pressure vessel, from where it was vented into the containment via water held in the pressure suppression chamber.

It was only when pressure in the containment had built up far beyond its design limit that steam was first vented from it at 04:00 on Saturday, March 12. Radiation levels of hundreds of millisieverts per hour in the building hours before that suggest that steam from the pressure vessel or containment escaped hours before it was supposed to have come out.

Direct seismic damage to pipes, valves or other components from the quake at 14:46 is a plausible explanation for a premature radiation release while the containment was supposedly still serving its function of holding back radioactivity from the environment. The local intensity of the quake was either close to or in excess of the design specification the reactors had been built to. For example, maximum seismic acceleration at unit 3 was measured at 507 gal in East-West direction, versus the 441 gal it was designed for.

So how does it matter if parts of Fukushima prefecture became uninhabitable because of broken steam pipes or because of flooded diesel generators? Isn’t the outcome the same? It’s actually a very important difference: Nuclear power companies in Japan are now taking measures to evaluate tsunami risks in plants around the country. Units 4 and 5 of Hamaoka NPP in Shizuoka were recently shut down because they’re located right on top of a quake fault line, but the plan is to restart them around 2014, after tsunami defenses have been beefed up around them. The problem is, even if — thanks to raised sea walls — the diesel generators were not knocked out by sea water, but the violent shaking were to destroy some other vital part of reactor such as cooling pipes, the outcome could still be the same.

Unit 4 blown up by leak from adjacent unit 3

The Wall Street Journal reports that TEPCO now think the hydrogen explosion that destroyed the service floor above the spent fuel pool in unit 4 was caused by hydrogen leaking from the adjacent unit 3, which also exploded:

Tepco also released its analysis of a hydrogen explosion that occurred at unit No. 4, despite the fact that the unit was in maintenance and that nuclear fuel stored in the storage pool was largely intact.

According to Tepco, hyrogen produced in the overheating of the reactor core at unit 3 flowed through a gas-treatment line and entered unit No. 4 because of a breakdown of valves. Hydrogen leaked from ducts in the second, third and fourth floors of the reactor building at unit No. 4 and ignited a massive explosion.

Adjacent units 3 and 4 are connected, for example by sharing a venting tower for the release of radioactive gases, which is located between them.

Nuclear expert Arnie Gundersen believes it is plausible that the particularly violent explosion that destroyed the top of unit 3 may have involved a criticality event (i.e. a chain reaction) triggered by the well-publicised hydrogen explosion.

See also:

TEPCO’s new cooling plan for Fukushima 1

After finding no water at all in the section of the reactor core of Fukushima 1 unit 1 that normally holds the fuel rods but instead finding 3000 tons of leaked water in the basement of the unit, TEPCO has abandoned its original plan and come up with a different plan to cool the reactor core.

Instead of trying to raise the water level inside the light bulb-shaped containment that surrounds the pressure vessel, which has not succeeded, it will spray water on to the reactor pressure vessel from above. The water will be pumped from the basement of the reactor, into which it appears to have been leaking and where it currently stands 4 m deep. It will be decontaminated to make it less radioactive before being recycled for cooling. A water decontamination unit built for TEPCO by French nuclear company AREVA is expected to arrive on Tuesday.

Reactors to be covered under tents

Meanwhile TEPCO has announced plans to cover units 1, 3 and 4 under tent-like polyester fabric sheets supported by a steel frame. The reactor building of unit 2 did not suffer a hydrogen explosion and therefore does not need covering. The tents may make it possible to filter radioactive steam and other emissions still rising from the reactor buildings whose cores are still beyond the boiling point and whose spent fuel pools are being cooled through water evaporation. Before the structure can be erected the vicinity of the blocks needs to be cleared of debris to make space for cranes and other construction equipment.

See also:

Uphill struggle to cool Fukushima 1 unit 1

After pumping increased amounts of water into the reactor core of Fukushima 1 unit 1 with the aim of bringing it to a “cold shutdown”, TEPCO had to conclude that the water level in both the reactor core and the containment is much lower than expected and their plan appears not to be succeeding.

Previously it was believed that the lower half of the fuel rods in the reactor pressure vessel (RPV) was covered in water. Now it appears that part of the RPV is dry and the fuel rods (or what’s left of them) are fully exposed. However, due to the damage to the rods much of the uranium pellets inside may already have spilled into the bottom portion of the RPV and may thus receive some cooling after all. TEPCO had only recently revised its estimate of core damage for unit 1 down from 70% to 55%.

The plan to provide ouside cooling to the RPV by flooding the dry well of the containment surrounding it with enough water to raise the water level to above the top of the fuel rods has not worked yet. Even after pumping more than 10,000 m3 of water, the water level in the 7,400 m3 containment is still below half, not even reaching the bottom of the RPV, let alone its top.

If the water level doesn’t rise further because of leaks then it seems quite unlikely that it will be possible to repair those leaks using manual labour, especially at dose levels of 10 millisievert and more per hour. Even when it looked like the plan might work for unit 1, it was questionable if the same procedure could then be applied to unit 2 or 3, which were already assumed to have a leaky containment.

TEPCO has not yet discussed any alternative plan if flooding the containment won’t work for some or all of the units.

See also:

TEPCO sends workers into unit 1 of Fukushima I

TEPCO has taken the first step towards installing new heat exchangers in wrecked reactors at its Fukushima 1 nuclear power plant that have suffered core damage after a cooling system failure. The objective is to achieve “cold shutdown”, which means that cooling water in the reactor remains below 100 degrees C and the pressure is at atmospheric level. Currently the water inside units 1, 2 and 3 is still boiling.

During normal operation, sea water cools steam coming out of the power turbine that generates electricity. It condenses it back to water, which goes back into the reactor core to be turned into setam again. After a shutdown, electric pumps and a separate heat exchanger, known as the residual heat removal system (RHR), take over the core cooling function. TEPCO had been aiming to restore the RHR since about March 20, when it reestablished a grid connection into the turbine hall, but found that the pumps are no longer usable.

The new system will not cool the core directly, which after the fuel rods partially melted is highly contaminated, but instead will circulate water to the containment vessel that surrounds the core, cooling the central part of the reactor from the outside rather than from inside. To that purpose, water will be pumped from a pipe connected to the containment to a heat exchanger, which passes the heat to an external water cycle that will be cooled using air. The original cooling system depended on sea water for condensing steam in the inner cycle, but the sea water intake system was flooded and destroyed by the tsunami, along with most of the diesel generators that provided power to all emergency pumps.

Before any work can be performed inside the reactor building, which no human had entered since the hydrogen explosions around March 12-15, the level of radiation there has to be brought down considerably. To that purpose a pair of hose pipes has been laid through the airlock and hooked up to a filter. Until at least May 16 air will be pumped through a filter set up outside the building. US-made robots sent into units 1 and 3 measured radiation levels of up to 49 mSv/h in unit 1 and up to 57 mSv/h in unit 3 on April 18. The dose inside the airlock of unit 1 was 270 mSv/h, in unit 3 it was 170 mSv/h. The typical background radiation dose for a civilian is 2-3 mSv per year. TEPCO hopes to be able to reduce radiation inside the building by a factor of 20.

Work will start with unit 1, because unlike unit 2 and 3 its containment vessel is assumed to be intact. Unit 2 and 3 are at atmospheric pressure. If they can’t maintain steam pressure they may also not hold water once they’re flooded. Also, because of a damaged torus (pressure suppression chamber), a lot more radioactivity has been leaking from unit 2 than from unit 1 and 3. That makes unit 1 by far the best candidate for trying out ideas on how to regain control and limiting further damage to the environment. However, there is no guarantee that, even if everything were to go perfectly on unit 1, any of the lessons learnt could be applied to the other units, since they may be too badly damaged to be repaired this way. The worst “patient” probably will be unit 2, which seemed to be leaking the most water. It isn’t clear how TEPCO is planning to deal with the leaking containments or the damaged torus. One approach might be to pump leaking water from the basement of the building back into the cooling system. TEPCO estimates 6 to 9 months for its “cold shutdown” plan.

Fallout prediction system went blind

Meanwhile it was reported that two systems meant to collect data from nuclear reactors and make predictions for nuclear fallout in Japan have failed to perform as intended. The Emergency Response Support System (ERSS) was supposed feed data from reactors into the System for Prediction of Envionmental Emergency Dose Information (SPEEDI). Both systems combined cost JPY 28 billion (about US$350 million), but ERSS failed along with everything else in Fukushima 1 when power was lost. It has yet to gather any data on the damaged units.

Radiation found on ocean floor

Caesium levels about 1000 times higher than normal have been found on the ocean floor 15-20 km from the Fukushima power plant, NHK reports:

The plant’s operator, Tokyo Electric Power Company, conducted its first contamination analysis of the seabed near the plant using samples from 2 points 20 to 30 meters deep on Friday.

Samples collected about 15 kilometers north of the plant contained 1,400 becquerels of cesium-137 per kilogram and 1,300 becquerels of cesium-134.

Samples taken around 20 kilometers south of the plant contained 1,200 becquerels each of cesium-137 and cesium-134 per kilogram.

The samples from the 2 points were also found to be contaminated with iodine-131.

TEPCO says it’s difficult to evaluate the readings as there are no official limits for these substances, but it will continue monitoring the radiation levels and their impact on seafood.

See also:

Fukushima watch 2011-05-01

The city of Koriyama in Fukushima prefecture, where top soil was removed from schools to reduce radiation exposure to children recently, is not only 50 km west of the Fukushima 1 nuclear power plant, it also lies in the heart of the central valley where most of the agricultural products of the otherwise mountainous region are grown.

Fukushima has already lost 90% of its fishing industry due to the tsunami. How much income will its farmers lose? Consumers can not be sure they will be safe if they eat crops produced in the region unless systematic testing takes place, but if high levels re found, farmers will demand compensation. How much will TEPCO have to pay and how much the government? In the 1950s nuclear power was sold to the public on the promise of being able to deliver electricity “too cheap to meter”. Now it could turn out as too expensive to measure.

Government advisor resigns in protest

Mr. Toshiso Kosako, a radiation export at the University of Tokyo has resigned as an advisor of the Japanese government, citing his opposition to raising permissible radiation exposure of school children. On April 19 the Ministry of Education and Scienced had announced a limit of 3.8 μSv/h (microsievert per hour), which is comparable to international maximum exposure rates of people working in nuclear power plants. Actually, 3.8 μSv/h times 24 hours times 365 days equals 33 mSv (millisievert), whereas in other countries the maximum permitted extra exposure on the job is 20 mSv, which comes on top of a natural radiation exposure of 2-3 mSv.

Radiation exposure of workers

Two workers at the Fukushima 1 nuclear power plant, employed by a sub-contractor of the power company, have been exposed to close to their maximum legal radiation dose:

The two workers have been exposed to 240.8 millisieverts and 226.6 millisieverts of radiation, respectively, when internal exposure is taken into account, among 21 workers exposed to over 100 millisieverts of external radiation since the crisis erupted following the magnitude 9 quake and tsunami, it said.

Under Japanese law, the Ministry of Health, Labor and Welfare has limited by an ordinance radiation exposure of each nuclear plant worker at 100 millisieverts a year in an emergency situation, but raised the limit to 250 millisieverts to cope with the Fukushima crisis on March 15.

The two were hospitalized for possible radiation burns to their feet after standing in water that contained radioactive materials 10,000 times the normal level while laying a cable underground at the troubled plant on March 24, the utility known as TEPCO said.

The limit for non-emergency work is 100 millisieverts over five years with no more than 50 per single year. These two workers received over 200 in a single month. The Ministry of Health and Welfare is planning to scrap the 50 mSv per year limit, leaving only the 100 mSv per five year limit in place for non-emergency workers. This is meant to make it possible to send workers from other reactors to Fukushima for cleanup work and still make it legal for them to absorb further radiation at regular work once they return.

Emergency power

TEPCO tested it’s mobile power generators at Higashidori nuclear power plant in Aomori prefecture on April 20 but revealed that the truck-mounted diesels had fuel for only 2 1/2 hours. If they have to provide power for longer they will need frequent refueling. In Fukushima 1 when the backup diesels failed it took about 9 days until grid power was restored inside the turbine halls to run electric pumps.

Radioactive contamination in unit 4 spent fuel pool

TEPCO has released updated numbers for radioactive contamination of the pool water in the spent fuel element pool of unit 4 of Fukushima 1. Here are the figures for 2011-04-29 (number for sample taken on 2011-04-13 in brackets):

  • Caesium 137 (half life: 30 years): 54,000 (was: 93,000 Bq/l)
  • Caesium 134 (half life: 2 years): 49,000 (was: 88,000 Bq/l)
  • Iodine 131 (half life: 8 days): 27,000 (was: 220,000 Bq/l)

Because 16 days have elapsed since the previous analysis, levels for iodine-131 should have halved twice (to about 55,000 Bq/l) while levels for both caesium isotopes should be virtually unchanged. Instead both caesium values dropped by more than 40% while Iodine is about 50% below the expected value. Where did the rest of the caesium and iodine go? There are several possible explanations.

Perhaps one of the analysises was simply wrong. That would not be out of the question, as TEPCO has had trouble with its figures before. More likely though, perhaps the water level was much lower on the first sample, meaning the current sample is diluted by a significant amount of added water (+72% water would explain the figures). That is to be hoped, because if the water level was in fact the same and the figures were correct then a lot of the pool water radioactivity would have had to escape into the atmosphere with steam or leaked with water to some other part of the reactor building.

Arnold Gundersen (YouTube, starting from 4:28) raised an interesting point about the isotope testing in the unit 4 pool: There’s too much iodine-131 for this to be from leaking fuel rods. The unit 4 reactor was shut down for maintenance on 2010-11-29, about 5 months ago. 151 days from 2010-11-29 to 2011-04-29 is close to 19 half lives for iodine-131, meaning only 2 millionths of the original iodine-131 levels should be left in the freshest nuclear waste in that pool, even less in older fuel rods. If 220,000 Bq/l came from atmospheric contamination (e.g. fallout from overheated unit 3 which is right next to it), then that is 220,000,000 Bq/m3 of water, left over after 4 half lives, so the original amount would have been 3,520,000,000. The pool is about 13m deep. To get it that radioactive, some 45,760,000,000 Bq/m2 had to land on the pool, which is a staggering amount.